PROGRES PEKERJAAN - 1. INDUK - 1.1.S/d hari ini sudah terlaksana 8-7-2022= 81 hari = 52,94% - 1.2.Sisa hari pelaksanaan : 72 hari - 1.3.Progres Riel : ...............................Tidak dibuat - 1.4.Rencana progres : .........SCHEDULE TIDAK ADA - 1.5.Deviasi Progres :...???????????????? - 1.6. Kontrak Exclude PAJAK = - 2.BIAYA - 2.1. TOTAL VOOR =2.391.912.353,83 - 2.2. Total REKAP Voor =2.391.912.353,83 - 2.3. Total CODE = 1.824.801.763,11
Friday, July 8, 2022
ReplyDeleteERMINTAAN BS OPNAM SUBCON PURWADI PERIODE 8 JULI 2022
Pengajuan code : 263.260.000
41 CII141 Upah Pekerja harian Purwadi " Mandor "
225,00 Hari @ Rp130.000,00 = Rp29.250.000,00
42 CII142 Upah Pekerja harian Pandi " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
43 CII143 Upah Pekerja harian Juwari " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
44 CII144 Upah Pekerja harian Diki " Pembantu "
225,00 Hari @ Rp100.000,00 = Rp22.500.000,00
45 CII145 Upah Pekerja harian Iqbal " Pembantu "
225,00 Hari @ Rp100.000,00 = Rp22.500.000,00
46 CII146 Upah Pekerja harian Sugik " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
47 CII147 Upah Pekerja harian Maji " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
48 CII148 Upah Pekerja harian Andi Wijaya " Ahli Scaffolding "
225,00 Hari @ Rp200.000,00 = Rp45.000.000,00
49 CII149 Upah Pekerja harian Eko Yuniarto " Ahli Scaffolding "
225,00 Hari @ Rp200.000,00 = Rp45.000.000,00
*************************
Opnam Minggu ini : Rp 15.910.000,01
Total Opnam sampai dengan Minggu ini : Rp132.960.000,01
90CII722
DeleteMohon yang lainya komentar agar Opnam bisa di lanjut
DeleteEVALUASI CHIYODA ---->S/D TGL 3-7-2022
ReplyDelete- Waktu Pelaksanaan
- 1. INDUK : 18-4-2022 s/d 18-9-2022 = 153 hari
- 2. KONTRAK PERKIRAAN = 2.210.895.807,86
PROGRES PEKERJAAN
- 1. INDUK
- 1.1.S/d hari ini sudah terlaksana 8-7-2022= 81 hari = 52,94%
- 1.2.Sisa hari pelaksanaan : 72 hari
- 1.3.Progres Riel : ...............................Tidak dibuat
- 1.4.Rencana progres : .........SCHEDULE TIDAK ADA
- 1.5.Deviasi Progres :...????????????????
- 1.6. Kontrak Exclude PAJAK =
- 2.BIAYA
- 2.1. TOTAL VOOR =2.391.912.353,83
- 2.2. Total REKAP Voor =2.391.912.353,83
- 2.3. Total CODE = 1.824.801.763,11
- 3.BIAYA DAN PROFIT
- 3.1. BIAYA RIEL S/D TGL 8-7-2022 =Rp1.097.654.905,98
- 3.2. PROFIT RIEL: ....??????? = -........??? (NEGATIF)
- 3.3. .......................
- 3.4. Stock Material :.= .......................????
- 3.5.PENYEBAB PROFIT
- 3.5.1. STOCK TIDAK AKURAT
PEMBAYARAN OLEH OWNER RS PETRO
1. Uang Muka =
2. Termin--->
OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 8-7-2022, BAYAR TGL 8-7-2022
ReplyDelete- NO. BKK : 90CII722
- KODE HARIAN PURWADI +SKAFOLDING :263.000.000,-
- PERMINTAAN OPNAM : 132.960.000,00
- KOREKSI : 132.960.000,00
- SISTEM : 132.960.000,00
- TERBAYAR : 117.050.000,00
- RETENSI :............
- SISA :15.910.000,-
- RENCANA BAYAR HARIAN PURWADI 8-7-2022:
- a. Kekuranagn 14-5-2022 = 0,-
- b. Opnam 8-7-22= 15.910.000,-
- c. Total = 15.910.000,-
PEMBAYARAN : OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 8-7-2022, BAYAR TGL 8-7-2022
- Rek. AGUS ARDIANSYAH (CHIYODA) : Diinput Mas Priadi
- Dibayarkan : 15.910.000,-
- NO. BKK : 90CII722 dan DATA Otorisasi Disiapkan Mas Priadi
Data pembayaran sudah disiapkan.
ReplyDelete