EVALUASI CHIYODA DAN TIDAK BISA MAKSIMAL GRESIK--->6-8-2022 - Karena GABUNGAN JO-Pak Candra - KONTRAK :2.210.895.807,86 - BIAYA - a. VOOR= 2.384.786.878,83 - b. Rekap Voor = 2.430.469.878,83 - c. Code= 1.925.728.709,06 - d. Permintaan +Borongan =1.272.550.210,38 = 42,44%
RENCANA - Waktu Pelaksanaan : 11-4-2022 S/D 31-10-2022= 195 HARI - TERLAKSANA S/D 6-8-2022 = 110 HARI = 56,41% - Sisa hari pelaksanaan :85 hari PROGRES : - RIEL PELAKSANAAN : 42,48% - Rencana progres : 39,04% - Deviasi Progres : 6,45% (Positif)
EVALUASI CHIYODA DAN TIDAK BISA MAKSIMAL GRESIK--->6-8-2022
ReplyDelete- Karena GABUNGAN JO-Pak Candra
- KONTRAK :2.210.895.807,86
- BIAYA
- a. VOOR= 2.384.786.878,83
- b. Rekap Voor = 2.430.469.878,83
- c. Code= 1.925.728.709,06
- d. Permintaan +Borongan =1.272.550.210,38 = 42,44%
RENCANA
- Waktu Pelaksanaan : 11-4-2022 S/D 31-10-2022= 195 HARI
- TERLAKSANA S/D 6-8-2022 = 110 HARI = 56,41%
- Sisa hari pelaksanaan :85 hari
PROGRES :
- RIEL PELAKSANAAN : 42,48%
- Rencana progres : 39,04%
- Deviasi Progres : 6,45% (Positif)
EVALUASI PROFIT
- Total Biaya s/d 24-7-2022 =Rp1.272.550.210,38
- Stock = 1.300.000,-
- Profit setelah stock = -354.399.595,73 = -37,73% (-) NEGATIF
- Note :
- a.
- b. Kontrak dgn RPL Upah saja
TAGIHAN :
1. Termin -1 progres fisik : 10%, dibayarkan 10%
2. Termin -2 progres fisik : 20%, dibayarkan 10% -
3. Termin -3 progres fisik : 100%, dibayarkan 60%
Termin-1 = Cair di anmdiri tgl 3-8-2022
Delete
ReplyDeleteSaturday, August 6, 2022
PERMINTAAN BS OPNAM SUBCON PURWADI PERIODE 6 AGUSTUS 2022
Saturday, July 23, 2022
PERMINTAAN BS OPNAM SUBCON PURWADI PERIODE 23 JULI 2022
Pengajuan code : 263.260.000
41 CII141 Upah Pekerja harian Purwadi " Mandor "
225,00 Hari @ Rp130.000,00 = Rp29.250.000,00
42 CII142 Upah Pekerja harian Pandi " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
43 CII143 Upah Pekerja harian Juwari " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
44 CII144 Upah Pekerja harian Diki " Pembantu "
225,00 Hari @ Rp100.000,00 = Rp22.500.000,00
45 CII145 Upah Pekerja harian Iqbal " Pembantu "
225,00 Hari @ Rp100.000,00 = Rp22.500.000,00
46 CII146 Upah Pekerja harian Sugik " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
47 CII147 Upah Pekerja harian Maji " Tukang "
225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
48 CII148 Upah Pekerja harian Andi Wijaya " Ahli Scaffolding "
225,00 Hari @ Rp200.000,00 = Rp45.000.000,00
49 CII149 Upah Pekerja harian Eko Yuniarto " Ahli Scaffolding "
225,00 Hari @ Rp200.000,00 = Rp45.000.000,00
*************************
Opnam Minggu ini : Rp 17.560.000,01
Total Opnam sampai dengan Minggu ini : Rp196.580.000,01
112CII822
DeleteOPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
ReplyDelete- NO. BKK : ...............CII822
- KODE HARIAN PURWADI +SKAFOLDING :263.000.000,-
- PERMINTAAN OPNAM : 181.830.000,00
- KOREKSI : 181.830.000,00
- SISTEM : 181.830.000,00
- TERBAYAR : 164.270.000,00
- RETENSI :............
- SISA :17.560.000,-
- RENCANA BAYAR HARIAN PURWADI 6-8-2022:
- a. Kekuranagn 14-5-2022 = 0,-
- b. Opnam 6-8-22= 17.560.000,-
- c. Total = 17.560.000,-
PEMBAYARAN : OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
- Rek. AGUS ARDIANSYAH (CHIYODA) : Diinput Mas Priadi
- Dibayarkan : ..............BELUM TUNTAS
- NO. BKK : ..........CII822 dan DATA Otorisasi Disiapkan Mas Priadi
OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
ReplyDelete- NO. BKK : 112CII822
- KODE HARIAN PURWADI +SKAFOLDING :263.000.000,-
- PERMINTAAN OPNAM : 181.830.000,00
- KOREKSI : 181.830.000,00
- SISTEM : 181.830.000,00
- TERBAYAR : 164.270.000,00
- RETENSI :............
- SISA :17.560.000,-
- RENCANA BAYAR HARIAN PURWADI 6-8-2022:
- a. Kekuranagn 14-5-2022 = 0,-
- b. Opnam 6-8-22= 17.560.000,-
- c. Total = 17.560.000,-
PEMBAYARAN : OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
- Rek. AGUS ARDIANSYAH (CHIYODA) : Diinput Mas Priadi
- Dibayarkan : 17.560.000,-
- NO. BKK : 112CII822 dan DATA Otorisasi Disiapkan Mas Priadi
Data pembayaran sudah disiapkan.
ReplyDelete