PERMINTAAN BS OPNAM SUBCON PURWADI PERIODE 6 AGUSTUS 2022

 




7 comments:

  1. EVALUASI CHIYODA DAN TIDAK BISA MAKSIMAL GRESIK--->6-8-2022
    - Karena GABUNGAN JO-Pak Candra
    - KONTRAK :2.210.895.807,86
    - BIAYA
    - a. VOOR= 2.384.786.878,83
    - b. Rekap Voor = 2.430.469.878,83
    - c. Code= 1.925.728.709,06
    - d. Permintaan +Borongan =1.272.550.210,38 = 42,44%

    RENCANA
    - Waktu Pelaksanaan : 11-4-2022 S/D 31-10-2022= 195 HARI
    - TERLAKSANA S/D 6-8-2022 = 110 HARI = 56,41%
    - Sisa hari pelaksanaan :85 hari
    PROGRES :
    - RIEL PELAKSANAAN : 42,48%
    - Rencana progres : 39,04%
    - Deviasi Progres : 6,45% (Positif)

    EVALUASI PROFIT
    - Total Biaya s/d 24-7-2022 =Rp1.272.550.210,38
    - Stock = 1.300.000,-
    - Profit setelah stock = -354.399.595,73 = -37,73% (-) NEGATIF

    - Note :
    - a.
    - b. Kontrak dgn RPL Upah saja

    TAGIHAN :
    1. Termin -1 progres fisik : 10%, dibayarkan 10%
    2. Termin -2 progres fisik : 20%, dibayarkan 10% -

    3. Termin -3 progres fisik : 100%, dibayarkan 60%

    ReplyDelete

  2. Saturday, August 6, 2022
    PERMINTAAN BS OPNAM SUBCON PURWADI PERIODE 6 AGUSTUS 2022

    Saturday, July 23, 2022
    PERMINTAAN BS OPNAM SUBCON PURWADI PERIODE 23 JULI 2022
    Pengajuan code : 263.260.000
    41 CII141 Upah Pekerja harian Purwadi " Mandor "
    225,00 Hari @ Rp130.000,00 = Rp29.250.000,00
    42 CII142 Upah Pekerja harian Pandi " Tukang "
    225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
    43 CII143 Upah Pekerja harian Juwari " Tukang "
    225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
    44 CII144 Upah Pekerja harian Diki " Pembantu "
    225,00 Hari @ Rp100.000,00 = Rp22.500.000,00
    45 CII145 Upah Pekerja harian Iqbal " Pembantu "
    225,00 Hari @ Rp100.000,00 = Rp22.500.000,00
    46 CII146 Upah Pekerja harian Sugik " Tukang "
    225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
    47 CII147 Upah Pekerja harian Maji " Tukang "
    225,00 Hari @ Rp110.000,00 = Rp24.750.000,00
    48 CII148 Upah Pekerja harian Andi Wijaya " Ahli Scaffolding "
    225,00 Hari @ Rp200.000,00 = Rp45.000.000,00
    49 CII149 Upah Pekerja harian Eko Yuniarto " Ahli Scaffolding "
    225,00 Hari @ Rp200.000,00 = Rp45.000.000,00

    *************************
    Opnam Minggu ini : Rp 17.560.000,01
    Total Opnam sampai dengan Minggu ini : Rp196.580.000,01

    ReplyDelete
  3. OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
    - NO. BKK : ...............CII822

    - KODE HARIAN PURWADI +SKAFOLDING :263.000.000,-
    - PERMINTAAN OPNAM : 181.830.000,00
    - KOREKSI : 181.830.000,00
    - SISTEM : 181.830.000,00
    - TERBAYAR : 164.270.000,00
    - RETENSI :............
    - SISA :17.560.000,-

    - RENCANA BAYAR HARIAN PURWADI 6-8-2022:
    - a. Kekuranagn 14-5-2022 = 0,-
    - b. Opnam 6-8-22= 17.560.000,-
    - c. Total = 17.560.000,-

    PEMBAYARAN : OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
    - Rek. AGUS ARDIANSYAH (CHIYODA) : Diinput Mas Priadi
    - Dibayarkan : ..............BELUM TUNTAS
    - NO. BKK : ..........CII822 dan DATA Otorisasi Disiapkan Mas Priadi

    ReplyDelete
  4. OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
    - NO. BKK : 112CII822

    - KODE HARIAN PURWADI +SKAFOLDING :263.000.000,-
    - PERMINTAAN OPNAM : 181.830.000,00
    - KOREKSI : 181.830.000,00
    - SISTEM : 181.830.000,00
    - TERBAYAR : 164.270.000,00
    - RETENSI :............
    - SISA :17.560.000,-

    - RENCANA BAYAR HARIAN PURWADI 6-8-2022:
    - a. Kekuranagn 14-5-2022 = 0,-
    - b. Opnam 6-8-22= 17.560.000,-
    - c. Total = 17.560.000,-

    PEMBAYARAN : OPNAM HARIAN PURWADI PROYEK CHIYODA TGL 6-8-2022, BAYAR TGL 6-8-2022
    - Rek. AGUS ARDIANSYAH (CHIYODA) : Diinput Mas Priadi
    - Dibayarkan : 17.560.000,-
    - NO. BKK : 112CII822 dan DATA Otorisasi Disiapkan Mas Priadi

    ReplyDelete
  5. Data pembayaran sudah disiapkan.

    ReplyDelete